TASK ORDER NO. 3
CONSULTING SERVICES
This Agreement is made and entered into as of the 6T" day of August, 2021 by and between
South Tahoe Public Utility District, hereinafter referred to as "DISTRICT" and Gannett Fleming,
Inc., hereinafter referred to as "CONSULTANT".
In consideration of the mutual promises, covenants, and conditions as addressed in the Master
Agreement dated June 10, 2019 and as specifically hereinafter set forth, the parties do hereby
agree as follows:
- n a
The purpose of this Task Order is for CONSULTANT to provide Emergency Engineering
Support Services to evaluate the immediate and future debris flow risk from the Tamarack
Fire to the Diamond Ditch, located in Alpine County, California, and to aid DISTRICT Staff
in both immediate protection of the facility and long term planning for the ditch.
CONSULTANT will provide a brief report documenting risks and recommendations for
remediation.
A full description of services is contained in CONSULTANT's written proposal "Task Order
No. 3 Request" dated August 6, 2021, and more specifically outlined therein by the Scope
of Work Items. This proposal is attached hereto as Exhibit "A", and by this reference is
made a part of this task order.
3. STAFFING
Services will be provided by Casey D. Smith, PG, CEG, Project Manager and
Memorandum Preparers William Millhone, PE, Memorandum Cosigner; Drew Kennedy,
PG, CEG, QC; Darren Mack, PE, GE, QC. CONSULTANT shall not change staffing
without approval by DISTRICT. Any changes shall provide for equivalent qualifications as
far as possible and practical.
4. TIME OF PERFORMANCE
Work for this Task Order No. 3 commenced upon verbal Notice to Proceed, issued by
DISTRICT Staff on August 6, 2021, and will be completed on or before October 15, 2021
unless otherwise directed by the District.
5. PAYMENT
Payment to CONSULTANT for services performed under this Task Order No. 3 shall be in
accordance with CONSULTANT'S "Project Budget Backup" (attached hereto as part of
Exhibit "A") for the persons assigned to the project tasks.
The cost ceiling for this Task Order No. 3 shall not exceed Twelve Thousand Six Hundred
Twenty -Six Dollars and Forty Cents ($12,626.40), and will not exceed same except as
provided in Article IV of the Master Agreement dated June 10, 2019.
All State of California prevailing wage laws must be complied with in the performance of
work related to this Task Order. These include, but are not limited to, Labor Code Sections
1720 through 1860.
7. EFFECTIVE DATE
This Task Order No. 3 will become effective upon execution by both parties.
IN WITNESS WHEREOF, this Agreement is executed by the General Manager and Clerk of the
Board of the South Tahoe Public Utility District, and CONSULTANT has caused this Agreement
to be executed the day and year first above written.
SOU HOE PUBLIC UTILITY DISTRICT
August 6, 2021
OH IEL, P.E., M.B.A. Date
GENERAL MANAGER ENGINEER
ATTESiv 1
L.. NIE G TTRY, tLEkK OF BOARD
GANNETT FLEMIN,G, INC.
By. 4 :f � '
DARREN MACK, P, E G.E.,
VICE PRESIDENT
2
E.v,�?flence t)eflveredAs Promised
To: Trevor Coolidge, PE
South Tahoe Public Utility District
1275 Meadow Crest Drive
South Lake Tahoe, CA 96510
From: Casey Smith, PG, CEG
Gannett Fleming, Inc.
2251 Douglas Blvd. Suite 200
Roseville, CA 95661
Date: August 6, 2021
Re: Diamond Valley Ditch Debris Flows — Engineering Support Services
Alpine County, CA
We have prepared this Task Order No. 3 request to provide engineering support services related to debris
flows that recently occurred along the approximate 1.4-mile section of the Diamond Valley Ditch, located
immediately northeast of the Harvey Place Dam in Alpine County, CA. The debris flows initiated due to a
combination of the active Tamarack Fire and recent thunderstorm events. The debris flows have led to
localized infilling of the ditch with silt to boulder sized materials that are currently preventing the operation
of the ditch. We understand that South Tahoe Public Utility District (STPUD) typically releases approximately
8 million gallons of treated effluent water per day from the Harvey Place Dam into Diamond Valley Ditch in
order lower the reservoir level for the winter months.
Given the urgency to return the ditch to service, STPUD intends to work directly with known contractors to
remove the current debris flow deposits from the ditch as part of an emergency project. STPUD has asked
Gannett Fleming to perform a site visit to meet with the contractors to observe site conditions and discuss
potential methods of reducing the risk of additional debris flows impacting the ditch both during debris
removal and once placed back into service.
SCOPE OF WORK
The following scope of work was developed based on the foregoing and conversations with STPUD
personnel.
• tcl Re nnaissance And Mee i
Mr. Casey Smith, PG, CEG, and Mr. William Millhone, PE will perform a site visit to meet with STPUD
and their contractors on the week of August 91h to: (1) review and photograph current site
conditions; (2) provide geologic and engineering support to STPUD during discussions with
contractors regarding potential near -term debris flow mitigation measures; and (3) discuss the
potential long-term mitigation measures that could be utilized to reduce future debris flow risk. We
assume that the site visit will comprise a total of ten (10) hours including travel to/from
Roseville, CA.
Gannett Fleming, Inc.
www.gannettfleming.com
• a
■
Task Order No. 3 Request — Diamond Valley Ditch Debris Flows — Engineering Support Services
Debris Flow Support
Page 2 of 3
• Summary Mempran lut a Pre aratiCrct
Gannett Fleming will prepare a brief memorandum summarizing the site reconnaissance
observations, onsite meeting, and our recommendations for the next steps including potential near -
and long-term approaches for mitigating future debris flows into the ditch. A draft version of the
memorandum will be circulated for STPUD review prior to finalizing. It is anticipated that the draft
memorandum will be submitted within one (1) week of the site visit. The memorandum will be
reviewed by two Gannett Fleming personnel in accordance with the Gannett Fleming Quality
Management System (QMS).
Perform project management tasks including project setup, invoicing, budget review and tracking,
staffing control, information distribution, and periodic check -in calls with STPUD. This includes up
to eight (8) hours of time to coordinate with the selected contractors regarding available materials
and their capabilities during memorandum preparation.
•
• Gannett Fleming does not assume the role of a "controlling employer" for work outside the
direction of Gannet Fleming, for jobsites under the supervision of a General Contractor or other
third -party entity, or for entities or persons with whom Gannett Fleming does not have a prime
contractual relationship. STPUD will retain and coordinate directly with the contractor(s) that will be
performing the debris removal.
• STPUD will facilitate safe access to the ditch. Gannett Fleming will perform a brief safety tailboard
meeting prior to beginning work to fill out and review a brief Job Hazard Analysis (JHA) worksheet.
• Due to the ongoing Tamarack Fire in the site vicinity, work will be performed under our Wildfire
Smoke JSA. If conditions such as increased fire activity or AQI>301 are anticipated or encountered
work may need to be postponed.
• Travel expenses will be billed in accordance with our Master Agreement for Consulting Services. It
is noted that Gannett Fleming personnel will travel in separate vehicles due to the ongoing
COVID-19 pandemic. Lodging is not included in this scope of work.
• It is anticipated that the summary memorandum will include conceptual sketches and/or
photograph markups depicting potential mitigation measures. Development of drafted figures or
formal engineering drawings is not included in this task order request. Further engineering or field
support will require a change order or a new task order.
Based on our understanding of the project we have tentatively assumed the following preliminary milestone
schedule. A final project schedule will be established at the start of the project.
Description Estimated Milestone Date
Receive Notice to Proceed August 6, 2021
Site Reconnaissance and Meeting August 10, 2021
Summary Memorandum (Draft Submittal) August 17, 2021
Summary Memorandum (Final Submittal) August 20, 2021*
* Assumes STPUD review comments are received on August 18, 2021
9
Gannett
Fleming
Task Order No. 3Request — Diamond Valley Ditch oebrisRows—sngneenngsunportsomice
Debris Flow Support
Page sm3
ESTIMATED FEES
Our estimated fee to perform the foregoing Scope of Work is $12'626 and will be billed on a 'time and
expenses' basis in accordance with the attached budget backup. We will not exceed the budget presented
above to perform the proposed Scope of Work. Should additional work, site visits, or meetings be required
in addition to the Scope of Work above, or should significant changes be required due to reasons beyond
the control of Gannett Fleming, STPUD will be notified, and the time required for these items will be billed
on 'time and expenses'basis. If this task order request is acceptable, please forward the necessary contract
documentation, referencing this Scope of Services, in accordance with our Master Agreement for Consulting
Services for our review and signature.
CLOSURE
We appreciate the opportunity to provide these services to STPUD. If you have any questions, please call.
Sincerely yours,
Caseyn. Srm7'i,PG, CEG #2679 Darren Mack, PE, GE#2634
Senior Project Geologist Vice President / Chief Geotechnica| Engineer
Attachments: Budget Backup
fiannerr
Project Budget Backup
Gannett Fleming, Inc.
Diamond Valley Ditch Debris Flows - Engineering Support Services
Site Reconnaissance and Meeting
Smith, Casey
Millhone, William
Expense: Mileage
Summary Memorandum Prenaration
Savko, Scott
Ul Haque, Syed
Smith, Casey
Millhone, William
Kennedy, Drew
Mack, Darren
Pro J#_ctKa"a ement/Coordinotlon
Smith, Casey
Millhone, William
Totals
10.00
$240.00
$ 2,400.00
10.00
$275.00
$ 2,750.00
440
$.56
$ 246.40
1.00
$130.00
$ 130.00
1.00
$190.00
$ 190.00
8.00
$240.00
$ 1,920.00
6.00
$275.00
$ 1,650.00
2.00
$320.00
$ 640.00
2.00
$320.00
$ 640.00
4.00
$240.00
$ 960.00
4.00
$275.00
$ 1,100.00
440 48.00
$ 12,626.40