TASK ORDER NO. 18
CONSULTING SERVICES
This Task Order is made and entered into as of the 18th day of October by and between
South Tahoe Public Utility District, hereinafter referred to as "DISTRICT" and Lumos and
Associates, Inc., hereinafter referred to as "CONSULTANT".
In consideration of the mutual promises, covenants, and conditions as addressed in the
Master Agreement dated November 20, 2014, and as specifically hereinafter set forth, the
parties do hereby agree as follows:
1. PURPOSE
The purpose of this Task Order is to authorize and direct CONSULTANT to provide
professional surveying services to complete the restoration of the remaining
property markers throughout the District's water service area that were disturbed by
the meter projects.
2. SCOPE OF WORK
The scope of work for these consulting services is further described in
CONSULTANT's four-page Proposal dated August 30, 2023. Said Proposal is
incorporated herein as Exhibit "A" and by this reference is made a part of this Task
Order.
3. STAFFING
Staffing will consist of Rick Byrem, P.L.S, WRS, Project Manager, and Michael
Craven, P.L.S, Field Work Supervisor. CONSULTANT shall not change staffing
without approval by DISTRICT. Any changes shall provide for equivalent
qualifications as far as possible and practical.
4. TIME OF PERFORMANCE
Tasks will be authorized to commence upon approval of DISTRICT's Board on
October 5, 2023, and shall be completed on or before June 30, 2025.
5. PAYMENT
Payment to CONSULTANT for services performed under this Task Order shall be as
provided in Article IV of the November 20, 2014, Master Agreement and shall not
exceed the amount of Three Hundred Fifty-Nine Thousand Three Hundred Eighty
Dollars ($359,380) unless the scope of work is changed, and an increase is
authorized by DISTRICT.
1
6. INSURANCE COVERAGE
CONSULTANT's Errors& Omissions coverage shall be $1,000,000 aggregate with
a deductible of not more than $100,000 for the duration of this Task Order.
7. EFFECTIVE DATE
This Task Order No. 18 will become effective upon execution by both parties and
shall serve as a Notice to Proceed upon execution by DISTRICT.
IN WITNESS WHEREOF, this Agreement is executed by the General Manager and
the Clerk of the Board of the South Tahoe Public Utility District, and CONSULTANT has
caused this Agreement to be executed the day and year first above written.
South Tahoe Public Utility District
P7,111 Hugh s(O t ),2023 8:15 P .T, October 05 2023
Paul Hughes, General Manager Board Approval Date
®flgfl499®4849i81Pt&;g8B81B
ublic
Attest �� �� :- > �rz,
Melonie Guttry, Clerk of Board .`
® S L
Aaabex
LUMOS AND ASSOCIATES, INC. I11111111
Oct 18 2023
e-?
Greg Phillips, Survey Manager Date
P.L.S. License No. 7936
2
EXHIBIT A
Carson City* El Dorado Hills& Fallon * Lake Tahoe Reno i"v
A�N Lake Tahoe
LUMOS Zephyr
Dorla Court, Suite 202 I PO Box 890
LUMOS
Zephyr Cove, Nevada 89448
- &A 1-1< � � 775,588,6490
August 30, 2023
LA23.756
Mr. Trevor Coolidge, PE
South Tahoe Public Utility District
1275 Meadow Crest Drive
South Lake Tahoe, CA 96150
Via email: tcoolidge@stpud.dst.ca.us
Subject REVISED 2023 Land Survey Proposal for Property Corner Replacements
South Tahoe Public Utility District, South Lake Tahoe, CA
Dear Trevor:
Lumos and Associates, Inc. (LUMOS) is pleased to provide you with this proposal for land surveying
services to replace multiple property corner monuments that have been disturbed or removed by
the District's water meter project.
Project Understanding
The proposed project is within the service area of the South Tahoe Public Utility District(STPUD) in
the South Lake Tahoe area of El Dorado County, California. It is our understanding that the scope
of work for this project will be to ultimately replace as many as 158 such property corners currently
identified by STPUD as needing replacement.
Project History
In October of 2021, LUMOS contracted with STPUD to replace an initial set of corners along Skyline
Drive in Tahoe Paradise Unit No. 14. These initial corners had been identified to serve as a "pilot"
project for the replacement of these specific corners only. The work was completed and a Record
of Survey was filed with El Dorado County in March of 2022 in Book 38 of Surveys at Page 22.
The intent with pursuing a "pilot" project was to allow both LUMOS and STPUD to evaluate the cost
and the procedures involved for the purpose of addressing additional work. The contract amount
was $4,000 plus review and recording fees. The actual billable time for the work performed by
LUMOS was $7,857, which equates to $1,571 for each of the five corners set. STPUD was only
billed for the contract amount.
The efforts of the"pilot" project were well received by the El Dorado County Surveyor's office as a
professional effort to replace and document the missing corners lost to the water meter project.
As a result of the above information, we propose the Scope of Services for the project found on the
following page.
EXHIBIT A
EXHIBIT A
August 30, 2023
Page 2
Project Scope— Property Corner Replacement
LUMOS will perform field surveys sufficient to replace each of the designated 158 remaining
property corners listed on the spreadsheet data provided by the District. Each property corner
will be replaced and monumented in accordance with the requirements of the California Land
Surveyors Act.
Upon completion of the field work for each corner, a determination will be made as to whether a
single Corner Record will prepared for each corner, or whether a Record of Survey drawing will be
prepared for a group of corners as was done in the 2021 "pilot" project.
Corner Records can only be utilized when the location of the re-established corner is substantially
consistent with the existing public record information for the subject property. If material
discrepancies are found between the existing adjoining property corners and the information found
in the public record, a Record of Survey will be required. A Record of Survey may also be
considered as a preferred option to individual Corner Records when a group of re-established
property corners can be combined into one exhibit, as was done in the 2021 'pilot" project.
Both Corner Records and Record of Surveys are reviewed by the El Dorado County Surveyor. The
Corner Records are indexed and kept by the County Surveyor, and the Record of Surveys are filed
with the County Recorder. All review and recording fees will be paid by the District.
Estimated Hourly Fees, For Each Corner:
Calculations (Pre & Post Initial Survey) 2hr @ $135/hr $270.00
Field Survey (Control &Set Corner— 2 visits) Or @ $330/hr** 1,320.00
Prepare Corner Record 2hr @ $135/hr 270.00
Supervision 390.00
Total $2,250.00
** Indicates the hourly rate for a two-person crew required to satisfy CA DIR prevailing wage rates
for El Dorado County.
The above fees are simply estimates. Work will be billed strictly on an hourly basis. Hourly rates are
inclusive of vehicle, equipment, and any other incidental charges. The hourly rates for the
anticipated contract period are shown on the attached fee calculator spreadsheet.
There will be opportunities for savings when corners are grouped in close proximity to one another.
It is our anticipation that we will work on setting multiple corners concurrently within specific
neighborhoods. There will obviously be times when conflicting evidence between adjoining corners
will require greater effort, and therefore, more time for each corner.
Invoices will be generated monthly for work completed during that billing period. Lumos will
provide information relating to the number of points set, records completed, and work in progress
during each billing cycle.
EXHIBIT A
EXHIBIT A
August 30, 2023
Page 3
Ell Dorado County Fees
LUMOS will pay the El Dorado County review fees, and pass those costs to STPUD with a 15%
processing fee added to the actual fee amounts. Those fees, not including the 15%, are as follows:
Corner Record Review $17 for each record
Record of Survey Review $135 for a 1-sheet map
Recording fee for Record of Survey $94 for a 1-sheet map
Schedule— LUMOS will be able to begin the field surveys, immediately upon approval of a
contract. We will work on the project, in conjunction with our other previously committed contracts,
until significant snowfall this fall. Work will resume upon snowmelt in the spring of 2024. It is
anticipated that all 158 corners can be set before significant snowfall in the fall of 2024. Corner
Records or Record of Survey drawings will be submitted to El Dorado County upon completion of
the field work for each corner, or set of corners.
Supervision &Certification
All work will be performed under the direction of a California licensed Professional Land Surveyor,
license number L-9129.
Field work will be scheduled and supervised by Michael Craven, PLS CA L-9685, from the Tahoe
office.
Thank you for allowing Lumos and Associates to provide you with this proposal. Please do not
hesitate to call me if you have any questions.
Sincerely,
Rick Byrem, PLS CA L-9129
Survey Project Manager
Cc: Greg Phillips, PLS,WRS, Director-Surveying Division
Michael Craven, PLS, Survey Project Manager-Tahoe Office
EXHIBIT A
EXHIBIT A
Page 1 LA23.7!
Project Name: 2023 South Tahoe Public Utility District Property Corner Replacement
Proposal/Job No: LA23.756
Date: 30-Aug-23
By: Rick Byrem
FEE SCHEDULE: Contract Rates through 12/31/2024
PW is 2 man rate set per El Dorado County Prevaling Wage flutes
Control: *County Fees include.15%processing mark
2 Man Crew COUNTY
Task Survey Tech 3 Project Manager PW FEES* Grand Total
135 /hr 210 /ir 30
Office/Prep 316 hr
Field Work 632 hr
Documentation 316 hr
Supervision 290 hr
Total Hours 632 t,:r 290 11x1° 632 hr 1,554 lea°
TOTALS $85,320.00 $60,900.00i,. ,4,'t,o Aux rs f t,w i11.: i
See letter proposal dated 813012023 for project assumptions and details.