HomeMy WebLinkAbout070721 Date: Wednesday, 7/7/2021 Project: Keller Heavenly Phase 1 Inspector:Aaron Zook, STPUD Crew on Site: Matt (Project Manager), Les (Operator), German (Laborer), Waggy(Laborer), Ricardo (Laborer) Equipment on Site: CAT 304C Loader, Work Truck, Work Truck w/Trailer, Dump Truck Daily Log: 8-9:30am: I was not on site. Contractor prepped for the days work and additional excavation in Herbert/Warr to expose unrestrained barrel couplers on both sides of tee. 9:30am: I arrive on site at Herbert and Warr. Chuck from STPUD heavy maintenance is on site welding tabs to restrain barrel coupler. 10:45am: Welding restraints complete. Chuck cleans up and leaves site. 10:50am: Contractor removing portion of concrete thrust block that is covering the flange. 11am: Concrete removal complete. Valves are closed and contractor cuts into existing main and begins dewatering at lower excavation in Herbert/Warr. 11:15am: Dewatering complete. Contractor cuts existing main to be abandoned at excavation in Herbert/Pioneer Trail. 11:20am: Begins unbolting flange on tee. 11:40am: Contractor installing blind flange on tee. Noon: Abandonment complete. Blind flanges are installed on tee at Herbert/Warr and on abandoned gate valve in Herbert/Pioneer Trail. 12:15-12:45pm: Contractor takes lunch 1pm: Begin backfilling excavation in Herbert/Pioneer Trail. Abandoned main has been capped with concrete plug. 1:30pm: Begins backfilling excavation in Herbert/Warr. 4:10pm: Contractor has completed backfill and temporary AC in both excavations. Herbert has been reopened. Contractor is moving traffic control materials to Janet/Pioneer Trail for abandoning valve tomorrow. 4:30pm: Contractor finished for the day. STPUD QUICK LOG Day & Date: L&�nzOo ' �r��� l Transcribe: Yes —x—No Project: Keller Heavenly Improvements Phase 1 (KLHV1) Contractor: White Rock Construction Company Inspector: Aaron Zook Today's Weather Forecast: Chance of Precipitation: 0 % �v K h., 4 � l Kz,t-,r �% S 1✓ w l� ! Q.rgv v,� J +t��, �✓S 15 u-j) 1--z> ZE>> c��� h. Crews and Equipment on site: 1 Project Manager I Operator s Truck Driver Foreman LaborerG-Qr.vGh �y�/ r�EGado EQUIPMENT Excavator 328 Loader 938M _Water Truck / 10 Wheel Dump Truck — Loader 928M Work Truck I Mini Excavator CAT 304 _Skip Loader Case 570MXT TC Truck Contractor Requests (shutdowns, pours, etc,): Tests: Service/Utility Hits: Potential Change Order Items/T&M: Work Completed Today: Notes: (Visitors, Incidents, Accidents): �i.,/ �cy .ter �;)-e ��r A.y war!� i- % �;�% �✓�e s�5'J r e q:� vv�i � ST P,) D In�u�/ v�r�il.i'"ev`��K. o w�0