Loading...
HomeMy WebLinkAboutfr_3247_5-11-23_ti DocuSign Envelope ID:902DCBD8-BE3D-4A81-8A74-76AA8957CD97 CONSTRUCTION Report No. MATERIALS FIELD REPORT ENGINEERS, INC. DATE JOB NO. 05/11/23 3247 Page 1 of 2 300 Sierra Manor Drive,Suite 1 PROJECT Reno, Nevada 89511 STPUD 2023 INSPECTIONS&TESTING SERVICES- phone(775)851-8205 TASK ORDER NO.21 fax(775)851-8593 LOCATION South Lake Tahoe,CA OWNER Adrian Combes South Tahoe Public Utility District CONTRACTOR SOUTH TAHOE PUBLIC UTILITY DISTRICT Vinciguerra 1275 Meadow Crest Drive WEATHER TEMP Clear/Calm 44 °F at 08:00 AM South Lake Tahoe, CA 96150 ss "F at PM PRESENT AT SITE: Vinciguerra Crew,Morgan and Dave,Wayne Vinciguerra THE FOLLOWING WAS NOTED CME personnel arrived onsite and reviewed plans in preparation for a pre con meeting scheduled for 10:00 am. Attendees at the meeting were Cuz, Larry, Star, Adrian and Trevor from STPUD, Mike with El Dorado County along with Wayne and Austin Vinciguerra. Concerns that were mentioned included the moisture condition of the existing soil and if it would be suitable for backfill, lift size, and frequency of testing. Mike asked for 12" lifts with testing being performed every 100'on each lift. It was also discussed that 95% compaction would be required on Black Bart and 92% on all other streets. The district also asked that in the event of a line being hit (regardless of who was at fault)that they would supply the parts but asked the contractor to supply the labor. Vinciguerra stated that would not be an issue. The contractor also stated that at this time they did not have a schedule or where they plan to begin on the Black Bart project but said they plan to begin Ham Lane first due to time restrictions (work can only be performed before Memorial Day or after Labor Day). After the meeting, went to Ham Lane where Vinciguerra had a pot hole operation being conducted. The 2 man crew was locating the 2" steel water line along with gas, electric and communications. The depth of the water varied between 33" and 40" at various locations They also looked for what was thought to be a 6" waterline that might extend on to Ham from Highway 50. No one was sure if there was one or where it might be located. The pot hole showed the 2"water 3, 4" conduits and black iron pipe believed to be 4". The contractor also laid out the saw cut lines with the hope of having him there Friday morning. At 5:00pm the contractor departed site.... FIELD DENSITY SUMMARY Gauge Info: Make: Troxler I Model: 3430 Serial No: Date of Calibration: Std Count Density Method of Measurement: Direct Std Count Moisture Soils Density Results: In-Place In-Place Optimum Maximum In-Place Specified Test Material Description: Elevation Test Dry Moisture Moisture Dry Relative Relative No. Depth Density Content Content Density Compaction Compaction Material Source: (in.) (PCF) (%) (%) (PCF) (%) (Min.%) *FG=Finish Grade/SG=Subgrade/RG=Rough Grade/OG=Original Grade/FTG=Footing Grade/BC=Base Course/Prefix B=Below IN HOUSE ROUTE TO: EMAIL: DS JVL V� Submitted by Tom Ingram