HomeMy WebLinkAbout06122023 STPUD QUICK LOG
Day & Date: 6/12/2023 Inspector: Bmclelland
Project: Heavenly keller phase 3
Contractor: white rock construction
Today's Weather Forecast: Chance of Precipitation: 80 %
Isolated showers and thunderstorms high 62 southwest wind 5 mph
Crews and Equipment on Site:
Superintendent _ Operator 2 Laborer
Foreman _ Operator/Laborer _Truck Driver
Carpenter _ Electrician
EQUIPMENT:
1 1.5 ton work truck 928 cat loader 305.5 cat excavator water truck
Work Completed Today:
the crew started working on new service to Sitzmark appartments. Due to existing utilities curb and concrete approach,most work was hand digging.
The crew excavated existing 10 inch ductile iron pipe and installed tapping saddle. They then hot tapped the main. Other personellwas digging out and
removing existng b36 boxes for reuse.
Notes:
0900 crew started working on site not all parts available so i was able to get the parts needed through UR Water
0915 begin excavation
1230 saddle installed on 10 inch main
1330 Begin setting up for hottap
1500 noticed Sitzmark of shut down tomorrow Hot tap completed. I was notified by pumps crew that there was no tank level to Keller tanks. i went up
to the tank and found valve closed to DP cell. i told Les to remove the hose bib they installed and put the sample port back on
Crew digging up tank road dug 70 feet of ditch for the day and will continue tomorrow
Test:
N/A
1